As a part of its three-phase project to bring natural gas to New Canaan public buildings, businesses, and hundreds of local homes, Eversource has released its construction schedule for the months of August and September. It was recently updated to “better accommodate the start of school,” according to company spokesman Mitch Gross.
The schedule is weather permitting and subject to change.
Crew 1 | Start | End |
Farm Road | 8/8/18 | 8/20/18 |
Harrison Avenue | 8/21/18 | 9/3/18 |
Kelley Green | 9/4/18 | 9/4/18 |
Orchard Lane | 9/5/18 | 9/5/18 |
Autumn Lane | 9/6/18 | 9/10/18 |
Crew 2 | ||
563-589 Hoyt Street | 8/6/2018 | 8/24/2018 |
Crew 3 | ||
Weed Street to Merritt Parkway
|
8/6/2018 | 8/17/2018 |
328-363 Hoyt Street | 8/20/2018 | 8/31/2018 |
Crew 4 | ||
Route 124 intersection at Farm Road | 8/6/2018 | 8/13/2018 |
Farm Road at Old Stamford Road | 8/14/2018 | 8/27/2018 |
Farm Road at South Avenue to White Oak Shade Road | 8/28/2018 | 9/4/2018 |
For more information about the project, including a map of the routes, visit Eversource.com.
Does anyone know when they are repaving? Farm Rd and South ave in particular?
The information about the natural gas construction schedule is mentioned above for South Avenue on Farm down through White Oak Shade Road:
August 28 through September 4 (weather permitting) or contact Eversource.com
If you mean repaving the roads after all of the natural gas expansion is done throughout the town, I would suggest asking DPW. They are on top of things.
When will the schedule for the Hinterlands, ie. Silvermine area, be published?